FG Secures $6.15bn For Power Infrastructure

401
POWER
A power official works on an electric pole along a street in Nigeria's commercial capital Lagos October 3, 2012.REUTERS/Akintunde Akinleye

FG Secures $6.15bn For Power Infrastructure

 

The Federal Government has said that it has secured $6.15 billion for infrastructural development in the power sector.

Minister of Power, Engr. Sale Mamman, who disclosed this in his report – One Year Anniversary: Key achievements.

 He stated in the report: “I am glad to state that to date, $6.15 billion have been secured for infrastructural development. The total sum has been earmarked for the following critical projects: $2.3 billion Siemens, $1.6 billion Transmission Rehabilitation and Expansion Programme, $1.7 billion DISP and $550 million NEP (WB/AFDB). “With the securing of the $6.150 billion in funding, the Federal Ministry of Power, under the present administration, has commenced the implementation of critical infrastructure that will enable the country to achieve generation, transmission and distribution of 25,000mw of electricity by 2025.

“We embarked on the biggest infrastructural development along the entire electricity value chain in the history of the Nigerian power sector.

“This development referred as Presidential Power Initiative aims to systematically up-rate end-to-end capacity of the bulk power system from generation to last-mile delivery, thus reducing system constraints, enabling wheeling capacity of power to be sufficient to drive industrial growth in the country as originally envisaged by the Economic Recovery and Growth Plan (2017).

“The initiative is structured into three phases, aimed at increasing power delivered to Nigerians to 7GW in the first phase (Phase 1), 11GW in the second phase (Phase 2), and 25GW in the third phase (Phase 3).

“The proposed Phase 1 projects, which we are about to commence, focuses on quick wins for both TCN and the Discos, with the objective of increasing power delivery to consumers by an additional 2GW, making a total of 7GW.

“The second phase will target the remaining last-mile bottlenecks to enable full use of the existing generation and ‘the last mile’ distribution capacities, bringing the systems operational capacity to 11 GW. “Phase 3 would involve developing the system up to 25GW capacity in the long term, with appropriate upgrades and expansion in generation, transmission, and distribution.

“To date, we have secured approval for the sum of $1.7 billion and $15.2 million for the Pre-Engineering work. A Special Purpose Vehicle (SPV) called ‘FGN Powerco’ is in the process of being set-up, following Mr President’s approval.

“The SPV will warehouse the project’s contingent liability for accountability. We have also constituted the Nigerian Project Management Office, PMO, with the sole responsibility of providing project management of the project on behalf of the Nigerian Government. Additionally, in a complementary way, we are also implementing the Transmission Enhancement Programme, TEP.

“The Federal Ministry of Power, working with key development partners – World Bank, AfDB and JICA – have raised $1.6 billion for Transmission Rehabilitation and Expansion Programme, TREP, which is on-going, with major projects, including Alaoji-Onitsha, Delta Power Station – Benin and Kaduna – Kano $410 million; $29 million is intended to build a 330kV DC 62km line between Birnin Kebbi and Kamba, Lagos/Ogun Transmission Infrastructure Project (JICA)-$200 million, Abuja Transmission Ring Scheme (AFD)-$170 million and Northern Corridor Transmission Project.” (AFD & EU)-$274 million.”

Current generation capacity and serves as the biggest source of base-load power that will improve grid stability. Economically, the project will enable job creation, drive entrepreneurial development, and unleash resource utilisation.

“The project contract was awarded in 2017 at the contract sum of $5.7 billion to the consortium of Chinese companies based on the agreement that the Chinese contractors will facilitate for Nigeria to secure concessionary financing of 85per cent ($4.85 billion) of the project cost from Export-Import Bank of China (China EximBank), while the Federal Government of Nigeria (FGN), will provide the remaining 15per cent ($850 million) consisting of $200 million loans from the Nigeria Sovereign Investment Authority (NSIA) and $650 million from direct FGN funding.

“The Mambilla Hydropower Project has a proposed installed capacity of 3,050mw. The main construction works include the following: Four large dams among which are the Nya Dam, Sumsum Dam, Nghu Dam, and the API Weir, two (2) Number 330KV – Abong powerhouse to Makurdi and 330KV – Abong powerhouse to Jalingo transmission lines with a length of more than 700kms, about 120km Access road network connecting the project site with nearby communities.”