‘Apapa-Wharf Road Reconstruction Only 10% Completed’

556

‘Apapa-Wharf Road Reconstruction Only 10% Completed’

The Apapa-Wharf Road reconstruction in Lagos State has achieved only 10 per cent completion, an official of the Federal Ministry of Power, Works and Housing (FMPWH), has said.

Mrs Olukorede Keisha, an FMPWH engineer supervising the project, said on Tuesday at the project site that presence of gas pipes and other public utilities in the road’s Right of Way (RoW) delayed the project execution.

She said that the contractors handling the project had, however, resolved the problem.

Keisha said that 200 metres of concrete road and 230 metres of drains had been constructed on section one of the project.

“The project is about 10 per cent completed; we finished 230 metres of drain and 200 metres of concrete road on section one.

“We have about four layers of road to make the pavement rigid; the road thickness is 600mm,’’ she said.

She said that the project had four sections.

Keisha said that a design alteration was done to take care of the gas pipelines in the RoW of the road so as to meet the completion date of June 2018.

“There is no need to relocate the pipelines again; the pipes are encased. We had to redesign in order to safeguard the pipes for work to continue.

“It is a shift in alignment, we shifted it forward,’’ she said.

She said that the redesign gave the opportunity for deep excavation to lay a solid foundation for a durable concrete road.

On potholes on some portions of the highway, Keisha said that rehabilitation work had begun on the bad portions.

According to Keisha, the ministry will use the Christmas holiday to take care of the most critical portions on the reconstruction zone and other roads in Apapa.